Whistler Road Report - August 7, 2009

Highway 99Alpine Paving will be continuing the Highway 99 Whistler Improvements Project along the Sea-to-Sky corridor on the south end of Whistler.  The Municipality of Whistler’s fire regulation restrictions have remained at the “Extreme” hazard level.  Therefore, construction within the interface – within 30 feet of the trees / underbrush – will continue to be on hold.  Only construction outside of the interface is permitted at this time.  As an early start time allowance for the project was to accommodate the 1pm finish time during the “High” hazard level, the hours of work for the project have been reverted back to original hours for construction - daily construction will now commence at 8:00am, Monday to Saturday.

(Please Note: In the event that the “Extreme” fire regulation restrictions are lifted, an update will be forwarded to stakeholders to advise them of the changes in the hours of construction.)

Upcoming Work Advisory

Please be advised that due to unforeseen circumstances, Alpine Paving was not able to complete all preparatory works required for the commencement of the work at Nordic Hill.  As a result, Alpine Paving has rescheduled the grade reduction roadwork at Nordic Hill for the week of August 17.  This phase of the contract entails placing road sub-grade on Highway 99 between Nordic Drive and Hillcrest Drive.  Due to the significant potential impacts to the traveling public, Alpine has decided to complete the work between the hours of 11:00pm and 6:00am.  During the scheduled work window, the permissible delays / closures include 30-minute delays during the entire shift (11:00pm to 6:00am), and temporary full closures from 3:00am to 5:00am, Monday to Friday.  Further details will be provided next week regarding the temporary closures / traffic delay impacts to the public during the scheduled works.

The following is the construction schedule and associated traffic control measures to be implemented:

Weekend Of: August 8 / August 9

Scheduled Work Activities:

  • Telus fibre optic cable installation along the east and west sides of Highway 99 between Alta Lake Road and Lake Placid Road;

Traffic Control Considerations:

  • Saturday, 8:00am to 5:00pm: Short sections of lane shifts / diversions along the length of the work area with less than 5-minute delays for traffic control personnel assisted truck access and egress;
**Please Note**  This work is not associated with the Highway 99 Whistler Improvements project.  However, as the work is taking place within the construction limits, we wanted to take the opportunity to notify you of the additional works.

Week Of: August 10 to August 15

Scheduled Work Activities:

  • Retaining wall construction and gas line installation on west side of Highway 99 (adjacent to southbound lanes) between Nordic Drive and Hillcrest Drive;
  • Hydro duct installation on the east side of Highway 99 (adjacent to northbound lanes) between Nordic Drive and Hillcrest Drive;
  • Grinding and paving works on the east side of Highway 99 (adjacent to northbound lanes) between Bayshore Drive and Lake Placid Road;

Traffic Control Considerations:

  • Monday to Saturday, 8:00am to 5:00pm: Short sections of lane shifts / diversions along the length of the work area with less than 5-minute delays for traffic control personnel assisted truck access and egress;
  • Monday to Thursday, 9:00am to 1:00pm / Friday, 9:00am to noon: Short sections of single lane alternating traffic patterns along the length of the work area with less than 15-minutes delays for off-loading materials and pouring concrete / backfill material;

Work by Others:

  • BC Hydro (subcontractor AllTeck) will commence underground line installation on the east side of Highway 99 (adjacent to northbound lanes) between Function Junction and Lake Placid Road;

Traffic Control Considerations:

  • Sunday to Saturday, 7:00am to 7:00pm: Short sections of lane shifts / diversions along the length of the work area with less than 5-minute delays for traffic control personnel assisted truck access and egress; 

Week Of: August 17 to August 22

Scheduled Work Activities:

  • Asphalt reclamation and grade construction on Highway 99 between Nordic Drive and Hillcrest Drive; **This work will result in a gravel road surface until the new grade is attained and the roadway is paved**
  • Hydro duct installation and shoulder reconstruction and paving works on the east side of Highway 99 (adjacent to the southbound travel lanes) between Bayshore Drive and Whistler Way; **Weather and Fire Hazard Level Dependent**

Traffic Control Considerations:

  • Monday to Friday, 11pm to 6:00am: Single lane alternating traffic patterns on Highway 99 between Nordic Drive and Hillcrest Drive with up to 30-minute delays;
  • Monday to Friday, 3:00am to 5:00am: Temporary full closures of Highway 99 between Nordic Drive and Hillcrest Drive;
  • Monday to Saturday, 8:00am to 5:00pm: Short sections of lane shifts / diversions along the length of the work area with less than 5-minute delays for traffic control personnel assisted truck access and egress;
  • Monday to Thursday, 9:00am to 1:00pm / Friday, 9:00am to noon: Short sections of single lane alternating traffic patterns along the length of the work area with less than 15-minutes delays for off-loading materials and pouring concrete / backfill material;

Work by Others:

  • BC Hydro (subcontractor AllTeck) will commence underground line installation on the east side of Highway 99 (adjacent to northbound lanes) between Function Junction and Lake Placid Road;

Traffic Control Considerations:

  • Sunday to Saturday, 7:00am to 7:00pm: Short sections of lane shifts / diversions along the length of the work area with less than 5-minute delays for traffic control personnel assisted truck access and egress;

During the hours of work, construction speed zones will be in effect so remember - traffic fines double in work zones – so please slow down!

Up-to-date Whistler weather reports are also available.

Looking for Whistler Lodging?

Aloha Whistler AccommodationAloha Whistler Accommodation offers over 75 quality Whistler lodging in Whistler Village, Blackcomb Benchlands, Whistler Village and Creekside.

2010 Olympic Whistler Accommodation

2010 Whistler Olympic accommodation is now booking as well! Choose from condos, townhomes and luxury home rentals.

And if you need help organizing your Whistler vacation we are here to help. Contact our in-resort, local travel experts today!

 



Add A Comment

Booking Options
Property Search
Arrival Date:
Calendar
Nights Stay:
 Guests:
The Whistler Insider
Whistler News - Whistler Events
Get FREE Whistler Updates by Email

We respect your privacy!

RSS Subscribe via RSS

Twitter Follow Us on Twitter

Bookmark and Share Bookmark/Share This Page

Categories

Archives

Vacation Rentals Blogs - BlogCatalog Blog Directory
Travel
blogarama - the blog directory